A photo of a fenced materials laydown area at the Ashridge Road, Darra project 

Construction of the new sewer main via open trenching started on 23 March 2015 and finished in mid July 2015.

Site restoration was completed by 31 July 2015.

Queensland Urban Utilities is committed to ensuring the long-term sustainability and efficiency of the region's water and sewerage infrastructure.

For this reason, we have installed a 430 metre long, 860mm diameter sewer line through park reserve on Ashridge Road and Monier Road, Darra, to increase the capacity of the local sewerage network to cater for heavy wet weather flows.

Construction of the new sewer main via open trenching started in March 2015 and finished in July 2015.